top of page

TTC service impacts due to track renewal starting February 17, 2025.

Writer's picture: BQNABQNA

Starting February 17, 2025, until late June 2025, the City of Toronto and the TTC will begin construction at the Bathurst Street, Lake Shore Boulevard West and Fleet Street intersection.


The construction will take place at Bathurst Street and Lake Shore Boulevard to renew aging streetcar tracks and replace the 105 year old water main. Complete streetscape improvements on Fleet Street including sidewalk widening and addition of public seating.


The work is being done in phases to keep traffic moving and avoid a full closure of the Bathurst Street and Lake Shore Boulevard West intersection.


TTC service impacts

In order to accommodate this construction, both the 509 Harbourfront and 511 Bathurst streetcars will be diverted. Starting Monday, February 17, 2025, until Saturday, March 29, 2025:


  • 511 Bathurst streetcars will operate from Bathurst Station to King Street West at Spadina Avenue.

  • 511B Bathurst replacement buses will operate from Bathurst Street at Queen Street West to Exhibition Loop.

  • 509 Harbourfront streetcars will operate from Union Station to Queens Quay West at Spadina Avenue.

  • 509B Harbourfront replacement buses will operate from Queens Quay West at Spadina Avenue to Exhibition Loop.


Construction phases and work hours

Construction is expected to take place over three phases from February 2025 to June 2025:

Work phase

Expected dates

Scope of work

Location

Phase 1A

February 17 to March 2025

Watermain replacement

The watermain running north-south along Bathurst Street, from the north side of Bathurst Street and Lake Shore Boulevard West intersection to just south of Fleet Street.

Phase 1B

March to late April 2025

Watermain replacement

The watermain running north-south along Bathurst Street, from the south side of Bathurst Street and Lake Shore Boulevard West intersection to the public lane south of the Esso gas station.

Phase 2

March to late April 2025

Streetcar track renewal

The streetcar track running north-south along Bathurst Street, from the north side of the intersection of Bathurst Street and Lake Shore Boulevard West to just south of Fleet Street.

Phase 3

Late April to June 2025

Streetcar track renewal

The streetcar track running north-south along Bathurst Street, from the south side of Bathurst Street and Lake Shore Boulevard West intersection to the public lane south of the Esso gas station.


Once the streetcar track renewal work is completed, from mid-May to June, the City's contractor will undertake restoration work and will complete the project. TTC crews will then test the newly installed tracks to ensure they are safe and reliable, prior to streetcar service resuming. The TTC anticipates regular service on the 509 Harbourfront and 511 Bathurst will resume by the end of June 2025.


During construction, TTC crews must work around the clock (24/7), specifically during new rail installation to preserve the integrity and quality of the new rail and concrete. Additional overnight rail work may include moving the new rail into position for installation.



Project links


City of Toronto Pre-construction notice



On October 9, Toronto City Council voted to endorse RESA option 1
The 509 Streetcar at Queens Quay West and Spadina












Commenti


I commenti sono stati disattivati.
bottom of page