Bathurst Quay Neighbourhood plan (BQNP) Implementation project update
Overview of key dates.
New waterfront promenade – Fall 2020 completion.
Transportation improvements – April 2020 construction start; Summer 2020 completion.
Ireland Park Interpretive & Cultural Centre Spring 2020 Consultation; Summer 2020 construction start. Summer 2021 opening.
New waterfront plaza & event space Fall 2020 consultation. 2020 Design; 2021 construction start; Phased opening 2021 and 2022.
TDSB sports field enhancements Spring 2020 consultation; 2020 Design; 2021 construction; Opening 2021.
Streetscape improvements Fall 2020 consultation; 2020 Design; 2021 construction; Opening 2021.
Canada Malting Silos rehabilitation Part 1: 2020 Design; 2021 construction start. Part 2: EOI/RFP late 2020/early 2021.
7. Canada Malting Silos rehabilitation: Part 1: Repair Scope of Work
Design, Tender Docs, Contract Admin & Construction Management for: – New roofing system – Power supply and roof anchor system – Exterior wall repairs – Heritage Conservation Plan – Removal of perimeter fence – Water and sanitary service investigation (co-ordinated with plaza design and construction)
Part 2: Repurpose